EDB Report Summary of Bids and Projects
CENTRAL
Quick Bids Completed since last quarter
Quick Bids Outstanding
· Ardingly Court (Jul-24): Benches £998.77. Two benches ordered Sept 24, one remaining, Simon Bannister to order remaining bench.
· Lavender House Social Club (Sept-24): Trip to Stanmer Park £190.00 to be paid end of Feb 2025.
· Leach Court (Jul-2024): Compost and bark £570.00 Simon Bannister to complete purchase.
· Leach Court (May-2024): Activity outings with minibus invoice pending. Total bid £675.00. £200 paid so far, Lucy Beasely to pay.
· Somerset Point (May-2024): Day trips with minibus invoice pending. Total bid £675.00. £200 paid so far, Lucy Beasely to pay.
Main Bids Completed since last quarter
Main Bids Outstanding
Craven Vale (Oct-22): Southwater Close allotment £6,193.00 – on hold until community workshop completion.
Essex Place (2020/21): lower existing bike racks – with Community Engagement Officer to progress.
Grosvenor Centre Management (May-24): Community room items £6,365.95. £4,000.00 remaining to spend, with Community Engagement Officer to progress.
Slone Court Tenants (May-24):Seated yoga classes £2,400.00. £1,800.00 paid, ongoing classes.
Transsober (Apr-23): Core running costs £6,272.40. £3,000.00 paid, ongoing.
Wiltshire House Residents Association (Oct-23): Deep clean of lobby and laundry room £1,320.00. With Community Engagement Officer to progress.
Craven Vale: Contribution towards Southwater Close Community workshop £10,000.00. On hold until further notice, funds ringfenced.
EAST
Quick Bids Completed since last quarter
· Bristol Estate Leaseholder and Tenant Association (Nov-24): Christmas events. £979.00 Grant funded Nov 24
Quick Bids Outstanding
None
Main Bids Completed since last quarter
None
Main Bids Outstanding
· Robert Lodge (Mar-22): Various items for Community Room £7,980.90. With Community Engagement Officer to progress.
· Wellsbourne Drop-In Café (May-24): Project funding £8,588.00. £5,725.00 paid, remaining payment due Mar 25.
NORTH
Quick Bids Completed since last quarter
· Jasmine Court Residents Association (Nov-24): Social events funding £1,000.00. Grant funded Nov 24
· Laburnum Grove (Sept-23): Waterbutt and guttering £800.00. Completed by Lee Sullivan Jan 25.
· Laburnum Grove (Jul-24): Seated yoga classes £1,000.00. Grant funded Jan 25
· Jasmine Court Residents Association (Sept-24): Seated yoga classes £1,000.00. Grant funded Jan 25
Quick Bids Outstanding
· Hornby Road (Jul-24): Planting £1,000.00. Seed and weed membrane ordered, remaining gardening to be confirmed by residents.
· Lindfield Court Garden and Social Club (Sept-24): Chair yoga £1,000.00. £900.00 paid, ongoing sessions.
· Holmstead (Mar-23): Plant pots and compost. £509.90. Ordered Nov 24, missed delivery of compost, waiting on resident confirming delivery date before reordering.
· Jasmine Court Residents Association (Jan-25): Seated yoga and chairs £1,000.00. EDB officer to pay.
· Lindfield Court Garden and Social Club (Jan-25): Seated yoga and chairs £1,000.00. EDB officer to pay.
· Hollingdean Residents Association (Jan-25): Contribution towards new oven for Community Room £995.00. EDB officer to pay.
· Laburnum Grove Social Group (Jan-25): Seated yoga classes £1,000.00. EDB officer to pay.
Main Bids Completed since last quarter
· Coldean Village Bingo (Nov-24): Running costs for bingo sessions £3,205.86. Grant funded Dec 24.
· Lindfield Court Garden and Social Club (Nov-24): Communal room items. £9,988.99. Grant funded Dec 24.
· East Moulsecoomb (2022/23): Improvements to path at Moulsecoomb woods £4,134.68. Completed by Lee Sullivan Jan 25.
· Action for Bevendean Community (Mar-24): New noticeboard £1,125.00. Completed by Lee Sullivan Jan 25.
· Highfield Road, Coldean (Oct-22): Excavate and install new block and slab steps with handrail, and a bench at the top of the pathway £3,6457.06. Completed by Lee Sullivan Jan 25.
· Moulsecoomb Local Action Team – The Bevy (Nov-24): Family Fun Day funding £9,986.00. Grant funded Jan 25.
Main Bids Outstanding
· Barcombe Place (Apr-22): Fence painting, new gate and garden sundries £1,194.66. £258.79 remaining, ongoing.
· Coldean (2022/23): Insulation and new heating to Coldean community building £9,192.22. Ongoing.
· Bates Estate Community Association (Nov-24): x8 new noticeboards £8,200.00. Ongoing
· Goodcycle (Nov-24): Cycle repair workshop £5,000.00. To be grant funded in instalments, ongoing.
WEST
Quick Bids Completed since last quarter
· Sanders House (Jul-24): Seated yoga classes £1,000.00. Grant funded Jan 25.
· Elizabeth Court (Sept-24): Seated yoga classes £1,000.00. Grant funded Jan 25.
Quick Bids Outstanding
· Muriel House Gardeners (Sept-24): Garden items £500.00. Scheme manager to update.
· Hazelholt (Jan-25): Seated yoga £1,000.00. EDB Officer to pay.
· Hazelholt (Jan-25): New microwave £80.00. EDB Officer to pay.
· Ingram Crescent Community (Jan-25): refurbish benches £1,000.00. EDB Officer to pay.
Main Bids Completed since last quarter
· Woods House Residents Association (May-24): Smiling Sessions singing activity £9,990.00. Grant funded Nov 24.
· Churchill House (Nov-24): Garden furniture £2,557.75. Grant funded Jan 25.
· Knoll Lunch Club and Forget Me Nots (Nov-24): Running costs for lunch club £2,796.00. Grant funded Jan 25.
· Hangleton and Knoll Community Action (Nov-24): Arts project £3,900.00. Grant funded Jan 25.
· Evelyn Court (Mar-22): Repainting of front wooden fence and wooden planters - Rub down and repaint in grey stain, front wooden fence and wooden planters at front of scheme £3,060.66. Completed by Lee Sullivan Jan 25.
· Muriel House (2020/21): Communal kitchen: new worktop, replace kitchen sink unit, relocate plug socket in cupboard. £3,125.00. Completed by Lee Sullivan Jan 25.
· Muriel House (Oct-22): New porch and tip-up seats £5,463.79. Completed by Lee Sullivan Jan 25.
· Evelyn Court (Nov-22): Garden items £1,236.00. Grant funded Feb 25.
Main Bids Outstanding
· Clarendon and Ellen (2020/21): Supply and install new galvanised key clamp railings to bin areas. Approved by CP&G. Work was never completed due to cars and a container obstructing the area.
· Clarke Court (22/23 Main Bid): Installation of water butts and storage solutions £1,500.00. Job Notes: Approved in April 22 by the West panel; storage grant sent to residents but no receipts received. Status of water butts uncertain.
Budget Summary by Area
Overall Totals
General Notes: